Lamson Road Carriageway repairs – closures

As you may be aware the carriageway has subsided at two separate locations along Lamson Road;  please see below dates for two way traffic signals / closure

Our proposal is to repair the carriageway and footway in three separate phases whilst minimising the disruption caused;

Phase 1 – works to start on site Monday 20th August 2018 for a duration of five working days. We are planning to use two-way temporary traffic signals between the hours of 8am to 4pm and no diversion route is required.

Phase 2 – Works to start on site from Tuesday 28th August 2018 for a duration of 15 working days. Due to the location of the subsidence the safest method of working is to close the entry in to Lamson Road from the Bridge Road roundabout between the hours of 8am to 4pm daily. The partial closure will assist operative to carry out the essential repairs safely and cause the least disruption within the area.  I have attached a traffic management plan for information.

Phase 3 – Full night time road closure on 24th September 2018 for two nights for carriageway surfacing in both locations. Time of closure is still to be confirmed along with the traffic management plan. Further details to follow

If you do have any further questions or comments please don’t hesitate toc contact me on the details below.

Kind Regards

Raj Padam MCIHT | Engineer